@benis_redux@cawfee.club For the first couple weeks :cirno_laugh:

Replies (1)

  • @CZB@eientei.org 2026-09-26 17:15

    @benis_redux@cawfee.club I think I'd do like 4" thick sand and make sure the clay under is packed super well... like wet it down weekly and pen up some cows in it for a month. Maybe after my footings are poured I'll backfill all my dirt and pen off the area. If the clay below is properly compacted I think I'll be fine. There will be cows on the feild I'm building on this winter so could just feed hay bales inside the area I want trampled.